2020 August Meadows Construction Bid Specs
Reconstruct approximately 7,200 square yards of asphalt roadway pavement with 5” of final compacted depth of hot mix asphalt pavement
Install offset staking prior to reconstruction to ensure proper alignment
Machine pulverize existing asphalt pavement and blend with underlying
subbase/subgrade materials
Machine mill transition joints at the reconstruction limits
Provide a tanker truck to water the pulverized materials during grading and compaction operations
Fine grade and compact the pulverized material with a 2% standard roadway crown
Proof roll the pulverized material with a loaded dump truck under the supervision of the village representative
Furnish and install (3.5” final compacted) depth MDOT 3C hot mix asphalt leveling course using PG 58-28 asphalt binder
Machine apply SS1H bond coat to the leveling course at the rate of 0.10 gallons per square yard
Furnish and install (1.5” final compacted) depth MDOT low volume superpave (LVSP) hot mix asphalt top course using PG 58-28 asphalt binder
Cleanup any debris generated by construction activities
Provide materials and construction methods that conform to the MDOT 2012 standard specifications for construction
Provide quality control testing of asphalt in a MDOT certified laboratory and provide the results to the village representative
Provide an onsite technician with a nuclear density gauge during paving operations to ensure that pavement density requirements are met
Provide hot mix asphalt job mix formulas (JMF’s) to the village representative for review and approval prior to construction
Provide hot mix asphalt mix designs and materials that meet MDOT requirements
Provide asphalt material samples for independent testing by the village representative
Provide a load ticket to the village representative for EVERY truckload of asphalt material generated from MDOT certified scales
Provide cumulative asphalt tonnages on load tickets to ensure that the proper amount of asphalt tonnage is placed on the project
Proposal is based on furnishing and installing 1,390 tons of MDOT3C hot mix leveling course
Proposal is based on furnishing and installing 615 tons of MDOT LVSP hot mix asphalt top course
Provide a (CREDIT) of $XXXX per ton for any tonnage underruns below the specified tonnage shown
No additional charge for tonnage overruns above the specified tonnage shown
All proposed pavement depths referenced are final, in place thickness after compaction
Optional Items of Work
Furnish and install 5’ width, clean, screened, topsoil shoulders along the new asphalt roadway, utilizing a road widener machine: ADD
Hydroseed the 5’ width topsoil shoulders: ADD
Provide a unit price for subgrade undercutting utilizing 21AA crushed limestone backfill:
$XXXX Per Cubic Yard
Quoted for the mid 2020 construction season (June-August)